TAWESCO shipping hall

New construction of hall 414/1 and a covered area for shipping TAWESCO products. Pile foundation, supporting steel structure, cladding made of sandwich panels, reinforced concrete floor, skylights in the roof of the hall, 4 sectional doors, new dispatch office, paved areas, new sewage, water, electricity lines.

Construction period: 06/2017 – 07/2018

What we did

  1. 01 Construction of foundations and piles
  2. 02 Steel structure with cladding
  3. 03 Concrete floors
  4. 04 Water and sewerage lines
  5. 05 Electricity lines

For more information, please do not hesitate to contact us. Contact us.

Our contacts

This website uses cookies.

We use cookies to personalize content and ads, provide social media features and analyze our traffic. We also share information about the use of our site with our social media, advertising and analytics partners. They may use the data together with other information they collect about you while using their services.